Case Study: Lab Setup and Network Management

Introduction

A) Project Background

1. Requirements Analysis :

  • The project required setting up a functional IT lab environment, which included organizing hardware, configuring network devices, and ensuring proper file sharing and OS installation.

2. Design and Concept :

  • The design focused on creating a well-organized lab with efficient network setup. The concept involved arranging hardware for optimal performance and configuring network devices to ensure seamless connectivity.

3. Plan the Project :

  • The project plan included tasks for hardware setup, network configuration, and troubleshooting. The timeline outlined phases for arranging hardware, setting up the network, and conducting tests.

4. Materials Procurement :

  • Materials included networking hardware (routers, switches, cables), tools for cable management, and software for network configuration and diagnostics.

5. Boxes Production :

  • “Boxes” in this context refer to the physical arrangement of lab equipment and network devices. This involved setting up server racks, organizing cables, and ensuring all devices were properly connected.

6. Boxes Assembly :

  • The assembly involved connecting all hardware components, configuring network devices, and ensuring that all lab equipment was properly installed and functional.

B) Planning Concept and Software

1. Planning Concept :

  • The planning concept involved creating a structured lab setup with organized hardware and efficient network configuration. Key aspects included cable management and network device configuration.

2. External Resources and Software :

  • External resources included network diagnostic tools and cable testing equipment. Software tools were used for configuring and monitoring network performance.

Project Scope Statement

A) Define Project Scope

The scope covered the physical setup of the lab, including hardware arrangement, network configuration, and ensuring connectivity. It also included troubleshooting network issues and optimizing file sharing.

B) Project Assumptions and Constraints

Quality

Assumed that all hardware and network configurations would meet performance and reliability standards. Quality was ensured through careful setup and testing.

Resources

Resources included networking hardware, cable management tools, and personnel for setup and troubleshooting.

Scope

The scope was limited to lab setup and network management, excluding broader IT infrastructure tasks.

Time

The project had a defined timeline for each phase, with deadlines for hardware setup, network configuration, and troubleshooting.

Work Breakdown Structure (WBS)

A) Decomposition

The work was decomposed into tasks such as hardware setup, network configuration, and troubleshooting. Each task was broken down into specific activities.

B) WBS

Hardware Setup

  • Arrange Server Racks

  • Install and Connect Devices

Network Configuration

  • Configure Routers and Switches

  • Set Up IP Addresses and File Sharing

Troubleshooting

  • Diagnose and Fix Network Issues

  • Ensure Connectivity and Performance

Project Schedule

A) Define Project Activities

Activities included user account setup, policy configuration, and testing of the ADDS environment.

B) Estimate Activities Duration

The duration for each activity was estimated based on complexity and required resources, with allowances for troubleshooting.

Charindu Neshmika

System Administrator

We've been There,
Done That.

All the tasks involved in this project are collaboratively done by Mr.Charindu Neshmika and Ms.Tharaka Liyanage.

Tharaka Liyanage

System Administrator